AI in construction: 6 uses for your own project data

How construction firms already use AI on hours, materials and invoices: tracking project margin, spotting overruns and asking questions from site.

Auke Westra

By Auke Westra

Founder of DigiData

Practical guide. This article covers the steps, checks, and common issues. View the Exact Bouw product page for supported data, operation and availability.

Short answer

For most construction and installation firms, the fastest gain from AI is not in robots or design software but in the data already in the project administration. An AI agent working on hours, materials and invoices from, for example, Exact Bouw and the accounting system shows how the margin develops per project, flags overruns before the project is finished and answers project managers' questions in plain language.

Where AI already helps in construction

When people think of AI in construction, they picture smart design software, drones or robots on site. For a typical construction or installation firm, the first gain is closer to home: in the hours, material bookings, projects and invoices already stored in the project administration and the accounting system.

That data is recorded every day but rarely used in time. Job costing comes after completion, project managers ask the office for figures, and management only sees the margin per project at month-end close. An AI agent that calculates on that data changes this without a new system on site.

1. Track project margin while the work runs

The basis is simple: invoiced revenue minus hours at cost price, materials and subcontracting. When hours and materials from Exact Bouw (formerly Bouw7) come together every day with invoices from Exact Online or Twinfield, you see the margin per project updated daily. You might ask the agent: "Which running projects are below a 15% margin?"

2. Spot overruns before it is too late

An alert works better than a report nobody opens. Set up a notification as soon as a project's hours or material costs reach 90% of the budget. With automations that check runs after every sync and the notification goes to the project manager by email.

3. Ask questions from the site

Project managers do not sit behind a dashboard. With the AI agent in Teams or Slack they ask from their phone how many hours were logged on a project this week, or which materials have not been invoiced yet.

4. Automate job costing

Job costing compares the estimate with reality per cost type. When hours, materials and invoices are connected, nobody has to put it together by hand anymore. Automate job costing explains which choices to make beforehand, such as the hourly rate.

5. A weekly report for project managers

Every Monday the status of their own projects in their inbox: hours logged against budget, material use and what can still be invoiced. That saves the office the weekly round of exports and emails.

6. Analyse hours

Where do the hours go? The agent splits hours per project, employee and activity and shows how many hours are not billable. That is often the fastest way to recover margin.

Worked example: seeing an overrun in time

BudgetSo farExpected at completion
Hours9006401,067
Labour (EUR 55 per hour)EUR 49,500EUR 35,200EUR 58,685
MaterialsEUR 38,000EUR 21,000EUR 35,000
MarginEUR 32,500 (27%)EUR 26,315 (22%)

Fictional example. Contract sum EUR 120,000; the project manager estimates the project is 60% complete.

Materials are on plan, but hours are not: at 60% complete, 71% of the hours are already used. Extrapolated, the project ends at 1,067 hours and the margin drops from 27% to 22%. Because you see this halfway, you can still adjust or discuss extra work with the client.

What you need

AI only calculates as well as the data that goes in. Check three things before you start:

  • Are hours always logged on a project, not on a general code?
  • Are materials and purchase invoices linked to a project?
  • Is it agreed which hourly rate you use for job costing?

Also record definitions, such as what you mean by margin and complete. Then the agent gives everyone the same answer.

How to start

Start small: connect Exact Bouw and your accounting system, pick two projects whose outcome you know and check that the figures reconcile. Then expand to all running projects.

Want to do that in one day with your own team? In the Exact Bouw training you build a project margin dashboard, a budget alert and a weekly report for project managers on your own data. More examples for the sector are on the construction and field service page.

Auke Westra

About Auke Westra

Founder of DigiData

Auke Westra is Founder of DigiData and writes about data integrations, OData and Power BI.